Road Stream Crossing Site GTBAY_ACE018

Acme Creek Watershed, Acme Creek East
Bunker Hill Rd
Acme Twp, Grand Traverse County
Information collected by:
Site Location
GPS Coordinates: 44.746537 , -85.444499
T27N R9W Sec 07
Owned by State
Fish Passability 0.9
Total Erosion: 0.8758 tons/year
Severity: Moderate
Year Inventoried: 2020
Inlet
Outlet
Upstream Conditions
Downstream Conditions
Road Approach - Left
Road Approach - Right
Crossing Information
Type of Crossing: culvert(s)
Structure Shape: Round
Inlet Type: Projecting
Outlet Type: At Stream Grade
Structure Material: Metal
Structure Substrate: Sand
General Conditions: Good
Structure Interior: corrugated
Dimensions of Structure: Length 40 ft. , Width 2.5 ft. , Height 2.5 ft.
Structure Inlet
Water Depth: 0.5 ft.
Embedded Depth of Structure: 0 ft.
Water Velocity*: 0.8 ft./sec.
Structure Outlet
Water Depth: 0.6 ft.
Embedded Depth of Structure: 0.2 ft.
Water Velocity*: 0.4 ft./sec.
*Water Velocities were measured 0.3 ft. below Surface (with Meter)
Stream Information
Stream Flow: Less than 1/2 Bankfull
Riffle Information
Water Depth: 0.4 ft.
Bankfull Width: 4.7 ft.
Wetted Width: 3.6 ft.
Water Velocity: 0.9 ft./sec. (Measured with Meter)
Dominant Substrate: Organics
Road Information
Gravel County Road
Road Condition: Good
Road Width at Culvert: 22 ft.
Location of Low Point: Other
Runoff Path: Ditch
Embankments
Upstream
Fill Depth: 0.5 ft.
Slope: More than 1:2
Downstream
Fill Depth: 0.5 ft.
Slope: More than 1:2
Approaches
Left Approach
Length: 300 ft.
Slope: 1% to 5%
Vegetation: Heavy
LS Factor: 0.46
Erosion: 0.8364 tons/year
Right Approach
Length: 130 ft.
Slope: Less Than 1%
Vegetation: Heavy
LS Factor: 0.05
Erosion: 0.0394 tons/year
Erosion Information
Total Erosion at Crossing: 0.8758 tons/year
Summary Information
Fish Passability 0.9
These non-native species were observerd at this site: Bull Thistle